For a site to be successfully awarded a contract it must meet the following criteria:

Each site must be within an active CMZ.  

Each site must be able to provide minute by minute metering data.

Each site must be able to respond within 15 minutes of receipt of a dispatch signal and hold the response for at least 2 hours.

 Each site will be required to build an Application Programme Interface (API), through which the site will receive dispatch signals and meter data will be issued to WPD.

Each site must be built or have a connection agreement with final milestone before the CMZs operating window.

Provision of the service must not put the participant in breach of other agreements (e.g. connection agreements).

Acceptance of WPDs CMZ Terms & Conditions